The Court case Nov 13 and 14. Update

NOV 14, 2017 — Save Chamberlain Park’s argument has been heard by the court and the argument for the Auckland Council was in the process of being presented before the court ran out of time. The case is adjourned until February 8th when the rest of the Council’s argument will be heard.
The court has asked the Auckland Council to resolve the interim position pending the delivery of the court’s judgment.
We therefore expect the council will undertake to postpone the start of any scheduled work planned for January 2018!! 
If, however, the Auckland Council is unwilling or unable to provide this undertaking to delay starting earthworks, the judge has reserved leave for Save CP Inc to return to him so that the question of interim relief can be dealt with by the court.